| State | Application form availability | Application fee | Approval time | Project completion time | Extension | Inspection |
| Andhra Pradesh | Online/Cash | Rs. 25 | 7 days | 90 days | 15 days | Yes (10 days) |
| Bihar | NA | NA | NA | NA | NA | NA |
| Chhattisgarh | Online | Connectivity charges: (50-100 kW) Rs. 10,000 (101-500 KW) Rs. 20,000 (501-1,000) Rs. 40,000 | NA | NA | NA | Yes |
| Delhi | Online | Rs. 500 | 30 days | NA | NA | Yes |
| Goa & UTs | Online | Rs. 50/kVA | 30 days | NA | NA | Yes |
| Gujarat | Online | Rs. 1,000 (residential) Rs. 10,000 (industrial) | NA | 12 months | No | Yes |
| Haryana | Online | Rs. 1,000 | 15 days | NA | NA | Yes |
| Himachal Pradesh | Offline (HimUrja) | Rs. 5,000 | NA | NA | NA | Yes |
| Karnataka | Online/Offline | Rs. 500 (up to 5 kW) Rs. 1,000 (5-50 kW) Rs, 2,000 (>50 kW) | 7 days | 180 days | NA | Yes |
| Kerala | Online | Rs. 1,000 | 15 days | 180 days | NA | Yes |
| Madhya Pradesh | Online | Rs. 2,000 | 30 days | 90 days | NA | Yes |
| Maharashtra | Online | Rs. 1,000 | 15 days | 180 days | NA | Yes |
| Odisha | Online | Rs. 500 | 15 days | NA | NA | Yes |
| Punjab | Online | Rs. 50/kVA Max Rs. 10,000 | 30 days | 180 days | 2 months | Yes |
| Rajasthan | Online | Rs. 200 (LT - 1 Ph) Rs. 500 (LT-3 Ph) Rs. 1,000 (HT-11 kV) Rs. 2,000 (HT-33 kV) | 15 days | 90 days (inter-connection) | NA | Yes |
| Tamil Nadu | Offline (TANGEDCO) | Rs. 100 | 10 days | 6 months | 3 months | Yes |
| Uttar Pradesh | Online | Rs. 250 (<50kW) Rs. 750 (50kW-1MW) | 30 days | NA | NA | Yes |
| Uttarakhand | Online | Rs. 500 per kW Max Rs. 30,000 | NA | NA | NA | Yes |